Project involved creation from scratch of a 24 bed girls dormitory including ensuites during the schools’ 2014 summer break using Pod Construction under a Design & Build Package.
Price Lilford were the Employers Agent
Ground works completed by Local Building Contractor FWD Construction with Elliott Modular Construction undertaking the Design & Build package.
- Planning Permission submitted 4/7/14 – received 20/8/14 (6 weeks and 2 days)
(actually received the day before we started craning in the pod units). - Cost – £900k net of fees and VAT.
- Programme
- Commenced on site
- Ground Works – 22 Jul
- Pods – 21 Aug
- Occupation – 22 September
- Commenced on site
- 5 weeks to build from scratch!
- 11 weeks from submission of Planning Application to Occupation
- £1900/sq m NET
- Who says you cannot build anything quickly and at a reasonable cost??